Controlled industrial demolition
A 1960s frame taken down in planned sections beside a live access road, with four material streams separated at source.
The constraint was not the structure. It was the access road running along the southern elevation, which had to stay open for the neighbouring units throughout.
Sequencing around a live road
We took the building down away from the road, working the high-reach from the north and dropping each section inward. The exclusion zone was re-marked every time the machine repositioned, and the spotter had authority to stop the work — which he used twice, both times correctly.
Sorting as we went
Strip-out first: fittings, timber, insulation. Steel recovered while it was still accessible. Then the frame in planned sections.
- Steel — 118 t, straight to the scrap merchant
- Clean concrete — 640 t, crushed on site
- Timber — 34 t, recovered
- Residual mixed — 8% by weight, the only stream that went to landfill
What it changed for the client
The crushed concrete became the sub-base for the replacement yard surface. One material stream never left the parcel: no gate fee, no lorry movements, no imported aggregate. On the final account, that was two line items that simply were not there.